Bellevue Pump Station Upgrade and Force Main Installation
Traffic detours and road closures
Update, Sept. 11, 2008 -- the Bellevue Pump Station Upgrade project begins in September. This project will require the closure of Southeast 6th Street between Southeast 6th Street Park and 102nd Avenue Southeast for the duration of the project.
Proposed Traffic Control Plan
- Southeast 6th Street will be closed between Southeast 6th Street Park and 102nd Avenue Southeast for the duration of the project. Traffic seeking to pass between 100th and 102nd Avenues Southeast will detour around the work site on Southeast 3rd Street and 101st Avenue Southeast.
- Southeast 6th Street Park will remain open to the public from 102nd Avenue Southeast via a temporary sidewalk extending around the northern and western border of the work site. The sidewalk in front of the pump station on Southeast 6th Street will be closed throughout the project.
- The work site and staging area on Southeast 6th Street in front of the pump station will be fully restored at the end of the project
Proposed Traffic Control Plan

For more information