History | The Plant | The Process | The People | Address and Contacts | More Information
|
Welcome to the Vashon Treatment Plant, located at 9615 SW 171st St., on Vashon Island in Puget Sound southwest of Seattle, Washington.
HistoryVashon Sewer District contracted with King County in 1999 to treat the wastewater of its customers. Then, the system was experiencing many violations. King County’s expertise in wastewater treatment and financing was needed to solve serious problems.
After taking over treatment plant operations in November 1999, the county carried out many interim steps to improve the plant. While the old plant was doing an adequate job, it was at capacity for the amount of incoming waste and flows. The old plant lacked backup systems. In addition to the treatment plant upgrades, the County advanced funds to the sewer district to build facilities to deal with health hazard areas at Bunker Trail and Beulah Park/Cove. Back to top |
|
||||
The Plant (upgraded in 2006)King County began building a new plant in 2004. Moving the marine outfall further out in the Puget Sound was completed in October 2004. Construction was completed in 2006 and an open house for the community was held in May 2007. The new plant and improvements were needed to meet regulatory requirements and to protect human health and the environment. This project was funded in part by loans from the Public Works Trust Fund, Washington State Department of Ecology and the US Environmental Protection Agency. Back to top
|
More plant photos |
||||
The ProcessThe Vashon Plant serves the Vashon Sewer District. The average normal flow is 90,000 gallons a day and the average wet weather flow is 180,000 gallons a day. The maximum plant flow capacity is 1.4 million gallons a day. Wastewater coming into the plant undergoes a series of treatments, including the following:
Back to top
|
The Vashon Plant discharges treated wastewater under permits issued by the Washington State Department of Ecology.
|
||||
The PeopleThe Vashon Treatment Plant runs 24 hours a day, seven days a week. At the plant, a state-licensed operator is responsible for the daily operations, performing analysis on processes and optimizing the plant's operations. Crews of mechanics and electrical and instrumentation staff, stationed at the South Treatment Plant in Renton, maintain and repair equipment. Our goal is to provide the region with the best wastewater treatment service available while operating as efficiently and effectively as possible. Back to top
|
|
||||
Address and Contacts Administration: 206-463-7318 9615 SW 171st Street Back to top
|
|
||||
More about Vashon :Links to .pdf files require the free Adobe Acrobat Reader to view.
Back to top |
|||||
|
Department of Natural Resources and Parks Updated: April 15, 2008
King County | Natural Resources & Parks | Wastewater Treatment Division Links to external sites do not constitute endorsements by King County. |