Feb. 10, 2006
King County to replace aging Lincoln Park sewer line
King County will start a four-month construction project this weekend
to replace more than a mile of sewer line that runs through West
Seattle's Lincoln Park. The aging line was damaged after heavy
rains and high flows on Jan.
17 and Feb. 6, causing sewage leaks in Lincoln Park.
The county is moving quickly to replace the 50-year-old line after
Wastewater Treatment Division inspectors discovered extensive wear
and corrosion throughout much of the pipe, which pushes wastewater
from the Barton Street Pump Station north of the Fauntleroy ferry
dock through a 6,250-foot pipeline to the county's Murray
Avenue Pump Station at Lowman Beach Park.
To keep the system operating normally during construction, crews
installed a temporary 6,000-foot-long, 18-inch-diameter surface
pipeline along the beach. The pipeline will carry wastewater from
an interim pumping facility at Barton to a manhole south of Lowman
Park where it will be discharged back into the system and go to
the West Point Treatment Plant in Seattle.
When the temporary pipe and pumping station begin operating this
weekend, the county will no longer need to bypass the damaged line
using trucks to haul wastewater from Barton to the Alki Treatment
Plant. The temporary pipe will also enable the county to stop bypassing
about a million gallons of wastewater a day to an outfall in Puget
Sound, which will protect water quality.
Contractors will begin permanent repairs next week. Installation
of a new, 24-inch plastic pipe inside the existing line will take
about a month to complete. Lining the old pipe is more efficient
and cost-effective because the old pipe will not need to be dug
out and removed.
When the pipe lining work is finished, the system will once again
begin normal operations and the temporary pipe along the beach will
be removed.
But because the new pipe lining will restrict capacity, King County
will need to spend three additional months installing a second 24-inch
pipe that will run parallel to the newly repaired line. Two pipes
will add enough capacity to increase system reliability, and allow
periodic inspections of each of the pipes.
Contractors will begin trenching along the beach in March, starting
from the south end of Lincoln Park heading north. King County and
City of Seattle Parks and Recreation are coordinating efforts to
get the work finished as quickly as possible.
The county will also be holding meetings with neighborhood groups
and the public to answer questions and address concerns.
King County's Wastewater Treatment Division protects public health
and water quality by serving 17 cities, 17 local sewer utilities
and more than 1.4 million residents in King, Snohomish and Pierce
counties. Formerly called Metro, the regional clean-water agency
now operated by King County has been preventing water pollution
for more than 40 years.