King County Navigation Bar (text navigation at bottom)

link to Wastewater Treatment Division home to Wastewater Treatment home pagelink to King Co. DNR home


Home

Project
Information

News and
Newsletter

Contract
Bids

Team
Information

Document
Library



Photos & Drawings


Signs

The CSO Project Unearths Seattle's Past

(Past and Present Photos of the Seawall Site)

The original shoreline in the area of Myrtle Edwards Park and Elliott Bay Park was in the vicinity of today’s Elliott Avenue West. The street and the first railroad tracks in this area were built on trestles. Over time, the shoreline was moved to the west by filling the trestle area and building new timber and rock bulkheads. Each time the shoreline was extended, the previous shore protection was buried in place. This piece of Seattle’s history became relevant to construction of the Denny Way CSO Project when geotechnical investigations revealed the abandoned seawalls lying in the path of the tunneling process.

As part of the Denny Way Project, three pipelines need to cross the 13 sets of railroad tracks west of the Elliott West site. Two of those pipelines will be deep - about 35 feet below the surface - and will be constructed using tunneling methods. The third pipeline needs to be closer to the surface because it will be used to drain stored flows from the tunnel to the Elliott Bay Interceptor (EBI), and therefore needs to be above the elevation of the EBI.

In order to avoid disruption of the Burlington Northern Santa Fe mainline tracks and the grain terminal tracks, the shallow pipeline will also be constructed by tunneling methods. However, geotechnical investigations during the design phase determined that tunneling this 72-inch pipeline would be very challenging, if not impossible, be- cause of two buried seawalls in the area where the tunneling will occur.

Tunnel machines of this size are not able to handle the large riprap boulders and timber piles that are located under the railroad tracks. One solution to this type of problem is to dig a hole and remove the obstruction when it is encountered by the tunnel machine. Of course, this is not practical with an operating railroad. Therefore, the project team discussed the problem with BNSF and Cargill staffs to identify a method to remove the seawalls so that the tunneling could occur successfully and the impacts to rail and grain terminal operations would be minimized. Because of the timing of grain shipments, Cargill suggested that the least disruptive times for them would be late summer and early fall.

The railroad crossing pipelines would be likely to be constructed in spring 2000. However, according to Cargill, spring is one of the busiest times of year for the grain terminal operations. In order to accommodate this schedule, King County decided to issue a separate contract to accomplish this work early.

In August, a contract was awarded to R.L. Alia, Inc. to remove the abandoned seawalls and replace them with a concrete-fill material that would be soft enough to tunnel through. This work required significant coordination with BNSF and Cargill to schedule the removal and replacement of the railroad tracks so that the work could proceed. As agreed with BNSF and Cargill, the work needed to be completed within seven days - from the time the tracks were removed until they were back in service.

In early October, Cargill’s schedule of grain trains and ships showed an opening, and Alia began the work of removing four sets of Cargill tracks, exca- vating the old seawall and backfilling the area with concrete fill. As soon as that work was completed, BNSF removed one set of its tracks, and the seawall under it was removed. Finally, the tracks were replaced, and Cargill’s operations were able to resume. All work was carefully coordinated with BNSF so that train traffic could continue as normal on the mainline tracks.

The seawall removal project is a small piece of construction work in the context of the entire project, but it is a good example of the County’s emphasis on minimizing risk of major problems during construction and working with the community to lessen impacts. Having taken care of the seawalls ahead of time allowed King County to minimize the potential of an unanticipated shutdown of the rail operations during Cargill’s busiest season.


For more information, e-mail or call Yvonne Kraus, community outreach coordinator,
206-269-0229, ext. 12.

Yvonne Kraus
Norton-Arnold & Co.
1932 First Ave., Suite 510
Seattle, WA 98101
Fax: 206-269-0249

Updated: November 12, 2001


King County | Natural Resources & Parks | Wastewater Division
News | Services | Comments | Search

Links to external sites do not constitute endorsements by King County.
By visiting this and other King County Web pages, you expressly
agree to be bound by terms and conditions of the site.
The details.