|
|
Along 42nd Avenue SouthStorage/treatment
tunnel, inlet & outlet regulators
|
 |
The Inlet and Outlet Regulator facilities were completed in August 2005. more photos |
 |
Inlet Regulator -- The 85-foot deep shaft was partially dismantled to build the facility’s equipment and chemical rooms. An at-grade structure was built above the shaft and underground rooms. Completion is scheduled for Spring 2005.
Outlet Regulator -- Work on the outlet regulator at 42nd Ave. S. and S. Norfolk St. is progressing and will be completed in Spring 2005. The new facility will incorporate a landscaped “green roof” to reduce storm drainage to the area. (August/September 2004) more photos |
 |
With tunneling completed in October 2003, current work is focusing on building the underground infrastructures at the Inlet and Outlet Regulator stations. At the 85-foot deep Inlet Regulator shaft, work consists of fabricating interior walls and vaults, building the chemical room, running electrical conduits and piping. At the Outlet Regulator, walls are being for formed and poured. In the coming months vaults will be fabricated and interior mechanisms set in place for wastewater screening and treatment. (June 2004) more photos. |
 |
The tunnel boring machine was removed from the receiving
shaft (north portal) in segments. The removal process took an entire
day. (October 27, 2003) more
photos.
|
 |
On October 20, 2003, the project reached an important
milestone when mining for 4-million-gallon wastewater storage and
treatment tunnel was completed. The 150-ton, 200-inch tunnel
boring machine (TBM) broke through a steel-reinforced concrete wall
into an open receiving shaft, 80-feet deep and 43 feet in diameter
at South Henderson Street and 42nd Avenue South. more
photos.
|
 |
Workers monitor ground settlement along the route of
the tunnel. (October 2003) more
photos
|
|

|
Aerial photo of the south portal. (October 2003)
|
 |
Each day the tunnel boring machine (TBM) advances further
north on its 3,100-foot trek from South Norfolk Street to South
Fairbanks Street. (August 2003) more
photos
|
 |
The tunnel operator advances the TBM from the head
of the tunnel. (August 2003) more
photos
|
 |
Concrete segments are fitted together to form tunnels
14-foor circular shell. (August 2003) more
photos
|
 |
As soils are mined, they are transported by conveyor
belt to rail cars (often called muck cars). When the
muck cars reach the tunnels south portal, soils
are transferred to a storage area and then hauled away from the
site by truck. (August 2003). more
photos
|
 |
The project's five smaller diameter tunnels are complete.
Three of these connect inside the two deep shafts. In mid-August,
the last of these five smaller diameter tunnels holed out
in the 85-foot deep MLK junction manhole, which is contained in
one of the two northern shafts. (August 2003) more
photos
|
 |
Tunneling on the large storage facility is now
underway. As the 14-foot diameter tunnel is mined,
soils are carried out on a conveyor belt and transfered to
"muck" cars, then lifted by crane and stored for hauling.
(June 2003) more
photos
|
 |
Tunnel boring machine (TBM) at the south portal (May
2003). The 150-ton, tunnel-boring machine (TBM) arrived May
12, 2003 and was set in the pit at S. Norfolk and 42nd Ave. S. by
huge cranes. Tunneling is scheduled to begin here at the south portal
in early June. more photos
|
 |
Deep shafts at northern end of storage/treatment tunnel.
Two deep shafts are under construction at the northern point of
the storage tunnel where the tunnel boring machine (TBM) will break
through later this year. (April 2003) more
photos
|
Along South Norfolk StreetPipeline
|
 |
Micro-tunneling under I-5 and the railroad tracks. Micro-tunneling is underway to cross beneath BNSF railroad tracks and I-5 at S. Norfolk St. and Airport Way S. May 12, 2003. more photos |
 |
Pipe Installation on S. Norfolk St. from Airport Way S. to East Marginal Way S. A 72-inch pipeline is being installed in an open trench from the west micro-tunnel portal at Airport Way S. and S. Norfolk St to the new King County manhole at East Marginal Way South and Norfolk. (May 2003) more photos |
Along South Henderson StreetPump Station |
 |
Work at the Henderson Pump Station was completed this spring. Expansion, which occurred primarily underground, doubled the capacity of the original structure that was built in 1974. The brick etched artwork on the east wall facing Seward Park Ave. S. titled Quest for Clean Water was completed in 1974 by well-known, artist Richard S. Beyer. (June 2004) more photos. |
Tunnel
Rescue Drill Photos
(click photo for larger view) |
 |
August 16th, the Seattle Fire Department, King County
and its tunnel contractor, NW Boring/Kenny JV, took part in a cooperative
tunnel rescue drill in order to provide firefighters and tunnel
workers rescue training inside a real tunnel. (August 16, 2003)
See also This Week in DNRP, Sept. 8, 2003 -- Firefighters
rescue two injured workers in simulated sewer tunnel fire
|