To protect public health and the environment, the King County Wastewater Treatment Division determined it must replace the aging Hidden Lake Pump Station and 12,000 feet of the nearby Boeing Creek trunk sewer in west Shoreline. King County also needed to build an underground wastewater storage pipe in Boeing Creek Park to help limit overflows to nearby Puget Sound. The 500,000-gallon storage pipe will store wastewater temporarily during peak storms. Construction is expected to run from summer 2006 through spring 2009.
Being a good neighbor during constructionKing County will work with the community
Project Schedule
For more information
|
|
|
||
|
Department of Natural Resources and Parks Updated: April 22, 2008 |
Related Information: Conveyance System Improvements City of Shoreline
|
|
|
King County | Natural Resources & Parks | Wastewater Treatment Division
Links to external sites do not constitute endorsements by King
County. |
||